NMU submitted a plan to the state last Friday to completely demolish John X. Jamrich Hall and Gries Hall and combine the two into one new building.
The rebuilding plan is to put the faculty offices that are currently located in Gries Hall into the new Jamrich building. The building will also consist of fewer large lecture halls and more smaller classrooms.
It will be located between the Learning Resources Center and C.B. Hedgcock. There will be a sky walk that connects the south east side of the new building to the LRC.
“NMU decided to go with the new building construction plan instead of a renovation and addition to Jamrich Hall because we could build the new facility for about the same cost,” said Cindy Paavola, NMU director of Communications and Marketing.
The new design would have great energy efficiency and better utilization of space, Paavola said. It would also reduce the university’s square footage by 36,000 square feet, approximately the size of Whitman Hall.
The new building would lower operating costs for NMU by about $180,000 per year compared to the renovation plan.
NMU’s original plan was to renovate Jamrich Hall and incorporate an addition of faculty offices.
However, Northern realized it could rebuild the building for around the same price as the renovation. The total cost of each project would be $33.4 million, and the state would fund 75 percent of it.
“So if the costs are equal but one offers reduction of costs in the long run, we are going to choose that one,” said James Thams, NMU associate director of engineering and planning.
Thams said he brought the rebuilding and renovation designs to the Marketplace a couple weeks ago, so students could provide input. He said the majority of students he talked to thought something needed to be done with the existing Jamrich.
The student opinion on which plan was better was an even split. However, the students were not able to hear all the benefits and drawbacks of the designs.
The rebuilding option was also chosen so NMU can continue to hold classes in Jamrich Hall while the new building is being worked on, Paavola said. Since about 40 percent of NMU classes are held in Jamrich, she said this is a big bonus.
“Seventy-seven percent of NMU courses have 40 students or less, yet only 28 percent of the classrooms in Jamrich match that capacity,” Paavola said. “So we will increase the number of 30 to 40 seat classrooms while decreasing the number of large lecture halls.”
In the new building, there will be a majority of 30 to 40-seat classrooms, some 20-seat, two 80-seat and one 150-seat classroom. There will also be a 500-seat lecture hall.
According to Thams, this is necessary for the large lectures that have about 300 students and for campus events such as Campus Cinema and visiting comedians.
“Additionally, the classrooms will have incredible flexibility to support active learning pedagogies, so if a faculty member likes to use groups in his or her class, the room will support that as easily as it does traditional lecture style and other forms of teaching,” Paavola said.
An example of the active learning classrooms that will be built can be seen in Room 108 at the LRC.
According to Thams, the intent of the new classrooms is to get as much technology and incorporate active learning classrooms as much as possible.
“The building will be designed in a way that better supports NMU’s high-tech learning environment,” Paavola said. “This includes enhanced power, higher ceilings to support new technology and new technology tools such as multiple screens.”
The faculty currently housed in Gries Hall, a renovated residence hall, will be moved to new, modern offices. This will move faculty closer to the academic mall and the classrooms they will be teaching in.
“The English department is spread out in two buildings and two floors,” Thams said. “The new building will give them one large suite.”
All faculty, adjuncts and teaching assistants from the English department, who currently have offices in Gries and Whitman Hall will be housed on the first floor.
Criminal justice and sociology departments will be on the second floor. The math department will be moved from the science buildings to the new Jamrich.
The psychology department will be moved to the science buildings to better accommodate the rooms needed. The Ada B, Vielmetti Health Center, currently located in Gries, is yet to be determined.
“The state has just received the project request and the committee that approves capital outlay projects has not officially approved the project yet,” Paavola said.
There are seven phases in rebuilding Jamrich Hall. Phases 100 through 500 are the design phases.
According to Thams, NMU is getting ready for phase 400 and 500, when they start to engineer the building. Phase 600 and 700 are the actual construction of the building.
“When the construction of the building begins will depend on state approval,” Thams said. “We hope to start construction in the spring and open the new building August 2013. It will be about a 15-month construction period.”
According to Paavola, the new building will benefit students and faculty by incorporating student learning areas, lounge areas and faculty offices all in close proximity.
“This will create an improved opportunity for faculty-to-student collaboration and a synergy of intellectual exchange,” Paavola said.
Josh S. • Nov 30, 2011 at 2:49 pm
As a recent graduate of NMU I suport the overall goal of the University. I do believe Jamrich and Gries need major overhaul. Neither is capable of keeping up with university demands. Jamrich is outdated and the space doesn’t reflect current student demands, making it a waste. Gries, while functional for offices is ill-apt to house classes. I had a psych. lab in there and it just isn’t workable. It is too narrow to hold classes. I do have concerns about parking. Parking is quickly becoming an issue at Northern…taking up a parking lot to build this is an issue. I thougtht we were putting a Student Union buidling in there? We do need one of thsoe as well. Either way, something needed to be done.
Zach B • Nov 14, 2011 at 8:05 pm
What will happen to Gries Hall once the teachers move out? I also wonder how Jamrich will be redesigned to house offices.
With regards to the previous comment- the state funds these construction projects. I’m a recent grad as well, and NMU deserves nothing but credit in keeping their costs low. Your tuition is going up because the state of Michigan is giving less money to educational institutions like Northern. Even then, look at the rate hikes of other schools, NMU has kept theirs low.
Matt H • Nov 13, 2011 at 12:15 pm
This is why your tuition keeps increasing!
Does anyone else find this ridiculous? What a waste! In the midst of a national and state budget crisis there is somehow room for 33,400,000 dollars to “fix” a building that is slightly outdated.
“The new building would lower operating costs for NMU by about $180,000 per year compared to the renovation plan.” So what the heck does that even mean? This sounds like incredibly short-term reasoning. That’s like when my girlfriend says she “saved money” because her jeans were 20% off. “But you still spent $60 dollars!”
In a situation like this, one only needs to follow the money. In this instance, look no further than the chairman of the NMU Board of Trustees, Brian D. Cloyd. Mr. Cloyd is a Steelcase man. And true to the words he spoke to me and other students throughout campus classroom visits in the Fall 2009 semester, Steelcase will no doubt be installing its Classroom 2.0 system through the new and improved Jamrich/Gries superhall.
1. As a former student, I know that new types of “learning pedagogies” (read laptops that do more to distract than teach(your annoying neighbor’s Facebook)) are often expensive and less effective than classical lecture/note taking.
2. As a recent graduate, I am glad I won’t be paying for this silly waste of money through my tuition.
3. As a taxpayer, I am annoyed that I will be paying for this silly waste of money. I also know better than to think NMU won’t get its shiny, new, expensive, gem of a teacher’s toy.
4. If class time is so important, save the $33.4 million and instead spend it on making a credit-hour last an actual hour! Hands-on instruction is the difference, a shiny new building with swiveling desks is not.
This is the link in case anyone is curious: CLASSROOM 2.0
http://www.steelcase.com/en/resources/insights-wall/pages/classrooms-2-0.aspx
(notice there is no mention of price, because this stuff is not cheap by any means)
Do the benefits really outweigh the costs in this case? It will take years to tell and this expenditure will be rolled into long-term debt, and so buried it will be too hard to tell.